Abstract

What makes a facility a Sensitive Compartmented Information Facility, and what can someone deciding today what to build or lease rely on? Three layers need to be kept apart. The first is the public documents: Intelligence Community Directive 705 of 2010 with its February 2024 technical amendment, two Intelligence Community Standards (705-1 and 705-2), and Technical Specification 1.5.1 of July 2021. The 1.5.1 transmittal describes modifications to Chapter 13, and comparison with the 2020 text finds one other changed rule. These documents set performance requirements and give illustrative constructions. The second layer is project decisions. A Certified TEMPEST Technical Authority recommends TEMPEST countermeasures, a named Accrediting Official approves construction, mitigations and accreditation, and a different official decides waivers. The third layer is industry reporting. AECOM’s conference slides describe a January 2025 ODNI memo with review and upgrade dates through 2028, and two firms report a May 2026 NCSC memo rescinding a plan-of-action requirement. A public search on 27 November 2026 found neither memo and no newer specification. Their scope and any surviving deadlines remain unverified.

A facility defined by a standard and an accreditation

Intelligence Community Directive (ICD) 705 states the rule in one sentence: “All SCI must be processed, stored, used, or discussed in an accredited SCIF.”1 DoD’s SAP manual defines a SCIF as “An accredited area, room, group of rooms, building, or installation where SCI may be stored, used, discussed, or electronically processed.”2 The facility stays accredited while it is inspected, documented and operated the way the accreditation assumed. The accreditation standard calls accreditation “the beginning of a life-cycle process of continuous monitoring and evaluation, periodic re-evaluations, and documentation reviews”.3

Three layers of requirement need to be kept apart: the public documents, the decisions they leave to named officials for a given project, and industry reports about policy that is not public.

The documents and how they fit together

DocumentDate in the published textWhat it does
ICD 705, Sensitive Compartmented Information FacilitiesSigned 26 May 2010; technical amendment signed 20 February 2024Policy: all SCI in accredited SCIFs; uniform requirements; accreditation; waivers; reciprocity; Chief of Mission facilities
ICS 705-1, Physical and Technical Security Standards for SCIFsEffective 17 September 2010Performance standards, overseas rules, waiver contents, roles
ICS 705-02, Standards for the Accreditation and Reciprocal Use of SCIFs22 December 2016Accreditation, re-evaluation, re-accreditation, de-accreditation, co-use and joint use
IC Tech Spec, version 1.513 March 2020Implementing specification: construction, alarms, access control, acoustics, devices, telephones, operations
IC Tech Spec, version 1.5.126 July 2021Transmittal: “modifications to Chapter 13” (Second Party officers); see below
DoDM 5105.21 Volume 219 October 2012, Change 2 effective 2 November 2020DoD SCIFs follow the ICD 705 series; DIA accreditation office; waiver and checklist procedures
DoDM 5205.07, Special Access Program Security ManualEffective 17 January 2025Replaces the SAP physical security volume; SAP areas follow the SCIF specification with stated variations
32 CFR Part 117 (NISPOM rule)eCFR text current to 24 November 2026Industrial security; contractor alarm approval; contractors follow IC directives and specifications for SCI
UFC 4-010-05, SCIF/SAPF Planning, Design, and Construction2023 edition cited here; WBDG lists an edition dated 30 September 2026DoD design criteria

Sources: the directive and amendment,14 the standards,53 the specifications,67 the DoD manuals,82 Part 1179 and the UFC catalogue.10

ODNI’s archived NCSC policy page lists ICS 705-01, ICS 705-02, Tech Spec 1.5.1, an older 2017 specification, and the version 1.5 forms (Pre-Construction, Fixed Facility, TEMPEST, Construction Security Plan, co-use and others). The page states that it has been archived and is no longer updated.11

The 2024 amendment. It states that technical amendments “are hereby made to ICD 705” and that the directive “as amended, reflects the establishment of the National Counterintelligence and Security Center (NCSC)”.4 In the amended text the Director of NCSC issues the IC standards, receives waiver reports and manages the SCIF inventory. The accreditation, waiver and reciprocity provisions read as in 2010.41 The amendment does not add construction requirements.

Tech Spec 1.5.1. Its transmittal “promulgates modifications to Chapter 13” of version 1.5, a chapter on Second Party Integree and Second Party Liaison officers (“Australia, Canada, New Zealand, and the United Kingdom”).7 A comparison of the two posted texts finds one other substantive change. In Chapter 2.C.2.c, version 1.5 allowed visitors in a Type III compartmented area only when material was stored out of sight “and no compartmented discussions occur”. Version 1.5.1 instead requires that the visitor be “under constant observation by a fully briefed person”.67 The 1.5.1 contents page moves Forms and Plans to Chapter 14, but the posted 125-page PDF ends with Chapter 13. The forms are posted separately.711 Chapter references below are to 1.5.1.

The UFC. The legacy WBDG catalogue lists the 26 May 2023 edition as “Active”.12 WBDG’s current catalogue lists UFC 4-010-05 with a publish date of 30 September 2026, describes its “Digital UFC Content” as “active for project delivery teams”, and adds a supplement, UFS 4-010-05, of the same date.10 A change summary dated 1 September 2026, provided “for information only”, says the six-sided design narrative and much TEMPEST detail moved to the UFS or to non-binding commentary.13 UFC passages quoted here are from the 2023 edition and are historical. DoD teams should confirm the applicable edition with the project authority.

ICD 705 replaced DCID 6/9.1 Facilities accredited under earlier rules “may continue to operate ... in accordance with physical and technical security requirements applicable at the time of the most recent accreditation or re-accreditation”, and must meet current requirements at re-accreditation unless a waiver is granted. The 2024 text keeps this clause.14 The cover memo of Tech Spec 1.5 dates ICS 705-1 to 27 September 2010, but the scanned standard reads “Effective: 17 September 2010”.65

Who decides

The head of each IC element may accredit, re-accredit and de-accredit, and may delegate this “to a single named official, who shall serve as the Accrediting Official” (AO).1 Waivers are decided by the element head or “a single named senior official, who could be the Cognizant Security Authority”, and “In no case may this official be the same person as the Accrediting Official”.4 The AO requests a waiver in writing, and a different official decides it.

ICS 705-1 and Tech Spec Chapter 3.A define other responsibilities. These are distinct roles, not a single chain of command.57

  • Cognizant Security Authority (CSA) in the IC documents: oversees its organisation’s construction and accreditation programme and keeps the SCIF repository current. Part 117 uses the same acronym for a different term. A Cognizant Security Agency is one of “DoD; DOE; NRC; ODNI; and DHS”.9
  • Accrediting Official: reviews and approves “the design concept, CSP, and final design for each construction project prior to the start of construction”; accredits; prepares waiver requests; may consider security-in-depth.5
  • Site Security Manager (SSM): develops the Construction Security Plan (CSP) in consultation with the AO, who approves it. The SSM inspects throughout the project and notifies the AO of deviations “within 3 business days”.57
  • Certified TEMPEST Technical Authority (CTTA): reviews plans “to determine if TEMPEST countermeasures are required and recommend solutions”, and gives the CSA and AO documented results. The CTTA recommends. The AO approves.5
  • Construction Surveillance Technicians: “Construction Surveillance Technicians (CST) shall only be required outside the United States when cleared contractors are not used.”5
  • SCIF Security Officer (SO): owns operating procedures, keys and combinations, self-inspections and the emergency plan (Chapter 12.C).7

In DoD, DoDM 5105.21 Volume 2 names the DIA Counterintelligence and Security Office (DAC) as AO, and lets DAC delegate to Combatant Command senior intelligence officials the approval of temporary working areas, temporary SCIFs and concept statements (Enclosure 2, paragraph 1.b). Waivers go through the CSA “to DAC for review”.8 For contractors, 32 CFR 117.23(a)(1) says: “Acceptance of the contract security measures is a prerequisite to any negotiations leading to program participation and an area accreditation (e.g., an SCI facility or SAP facility accreditation).” Section 117.23(b) says “contractors will follow Intelligence Community directives, policy guidance, standards, and specifications for the protection of classified national intelligence and SCI”.9

From concept to accreditation

ICS 705-1 says “all SCIF planning shall begin with sponsorship by an AO”.5 The Tech Spec says security plans “should be coordinated with the AO before construction plans are designed, materials ordered, or contracts let” (Chapter 2.A.2).7 The documents set dependencies, not one fixed order.

  • Concept. The Pre-Construction Checklist may go to the CSA and AO as part of concept approval (Chapter 3). It is meant to tell them what is needed “to determine the minimum security requirements for final SCIF accreditation”.714
  • Risk assessment. Chapter 2.A says the AO and SSM may conclude that a standard is better mitigated, or that more measures are warranted by a significant risk factor.7
  • TEMPEST. The TEMPEST checklist goes to the CTTA for a countermeasures review.1516
  • CSP before contract award. “Prior to awarding a construction contract, a CSP for each project shall be developed by the SSM and approved by the AO” (Chapter 3.B.1).7
  • Fixed Facility Checklist (FFC). DoD guidance says to submit it “around the end of the design phase”, update it during construction, and complete it with the TEMPEST addendum before the SCIF is finished.8
  • Inspection and accreditation. The AO or designee inspects and reviews the FFC, operating procedures, emergency plans, CSP and any waiver packages. Under ICS 705-02 §D.2.b, “A TEMPEST review and verification of countermeasures by a Certified TEMPEST Technical Authority is a necessary part of the accreditation process”. Whether the review and evaluation are included in the accreditation documentation depends on whether the AO requires it. A TSCM inspection may be required for a new SCIF or significant renovation “when deemed necessary by the AO”. The letter of accreditation records storage type, acoustic status (“discussion or non-discussion, amplified or non-amplified”), date, a statement that the SCIF meets “all physical, TEMPEST, and technical security standards in place”, and any waivers.3

ICS 705-1 says SCIF plans and diagrams must never be sent or posted on unprotected systems or the Internet without encryption.5 The 2020 DoD manual required protection of a SCIF’s location and identity “at a minimum of FOR OFFICIAL USE ONLY (FOUO)”. It also asked that releasable documents such as bid requests, permit requests and subcontractor plans call the space a controlled space, without naming it a SCIF.8 FOUO is a legacy marking. DoD’s CUI instruction does not require legacy-marked documents to be re-marked while they stay under DoD control. Legacy information does not automatically become CUI and must be reviewed by its owner. New documents derived from legacy material must be marked if the information qualifies as CUI. Existing legacy documents being shared outside DoD must also be marked when they qualify, subject to the instruction’s exception for access to DoD-controlled websites or databases.17 The DoD CUI Registry (opens in a new tab) lists building plans that reveal SCIF design or construction as an example under Physical Security. Confirm the category and markings with the sponsor.

What kind of SCIF

ICS 705-1 §F.2 defines the facility types and warns that “a facility accredited for closed storage and non-amplified discussions is not reciprocal for open storage and amplified discussions”.5 Storage, discussion and occupancy are separate attributes.

  • Closed storage “requires all SCI material to be stored in a GSA approved security container”. Open storage “allows SCI to be openly stored and processed within the SCIF”.5
  • Secure Working Area (SWA): SCI handled, discussed or processed “but where SCI is not stored”.5
  • Temporary Secure Working Area (TSWA): SCI use “less than 40 hours per month”. Chapter 3.J limits accreditation to 12 months or less and says “Storage of SCI is not permitted within a TSWA”. “No special construction is required”, but a TSWA approved for SCI discussions must meet Chapter 9, and “The AO may require an alarm system.”57
  • Continuous operation: “staffed and operated 24 hours a day, seven days a week”. Occupancy is separate from storage and acoustic authorisation.5
  • Temporary SCIF: for “tactical, emergency, or immediate operational requirements”.5

Compartmented Areas separate programmes within a SCIF. Type I is for viewing and processing without storage or discussion. Type II is for discussion and must meet STC requirements. Type III allows storage. Its visitor rule is the one that changed in 1.5.1 (Chapter 2.C).7

The type determines which requirements apply. ICS 705-1 §G.1 requires every SCIF perimeter to “provide a physical barrier to forced, covert and surreptitious entry”.5 Within that duty, the Tech Spec’s fixed-facility construction guidance says closed-storage areas “that do not require discussion areas do not have any forced entry or acoustic requirements”, and that open storage without security-in-depth needs “additional protection against forced and surreptitious entry” (Chapter 3.C.1). For overseas SCIFs outside Chief of Mission authority, Chapter 4 separately sets a five-minute forced-entry standard for closed storage and allows AOs to deviate from the chapter’s guidance in Categories II and III where effective security-in-depth supports it.7 A room accredited for capabilities its contracts do not need takes on requirements its mission does not use.

The perimeter, threat by threat

ICS 705-1 lists the threats: “compromising emanations, inadvertent observation or overhearing, disclosure by unauthorized persons, forced entry, and the detection of surreptitious and covert entry”.5 The standards state performance requirements. The Tech Spec gives constructions that meet them, and the AO may approve others.

Forced, covert and surreptitious entry

The perimeter “includes all perimeter walls, windows and doors as well as the ceiling and floor”. Walls, floor and ceiling “shall be permanently and solidly constructed and attached to each other”, and raised floors and false ceilings “shall not be used to anchor wall support materials”. The standard also says: “All construction, to include above the false ceiling and below a raised floor, shall be constructed to provide visual evidence of unauthorized penetration.”5 Floors and ceilings meet “the same standards for force protection and acoustic protection as walls” (Chapter 3.D).7

The Chapter 3.C wall types are “suggested”. Requirements vary “by the type of SCIF, location, use of SID, and discussion requirements”, and an existing wall of “substantial material (e.g., brick, concrete, cinderblock, etc.)” that meets the standard may be used.7 DoD guidance calls the Tech Spec methods “an accepted way to meet the performance standard, but there may be several ways to achieve the same standard”, provided the alternative is recorded in the FFC and approved by the AO.8

Suggested assembly (Tech Spec 1.5.1)Circumstance the spec namesDecision it affects
Wall A, standard acoustic: three layers of 5/8 inch gypsum board with acoustic fill, “Sound Class 3” (§3.C.2)Closed storage, SWA, continuous operation, or open storage with security-in-depthAcoustic performance; evidence of penetration
Wall B (expanded metal) or Wall C (plywood) (§3.C.3)Open storage without security-in-depthAdded resistance to forced and surreptitious entry
Vault: GSA modular vault to AA-V-2737 or reinforced concrete; steel-lined construction only “Where Unique Structural Circumstances Do Not Permit Construction of a Concrete Vault” (§3.C.5)Where a vault is requiredStorage protection; GSA-approved Class 5 vault door

The Tech Spec warns that “Advertised claims by manufactures that their product(s), to include mobile platforms, prefabricated structures, containers and modular structures are built to SCIF standards and can be accredited without modification may not be accurate” (Chapter 2.A.2.a).7

Doors, locks and access control

Chapter 3.E requires “only one Primary door”, with an FF-L-2890 deadbolt, an FF-L-2740 combination lock and an approved access control device. Previously AO-approved hardware may remain. Secondary doors need AO approval. Emergency egress-only doors are “alarmed 24/7”. Perimeter doors have non-hold closers, protected hinge pins, alarms, acoustic performance “unless declared a non-discussion area”, and TEMPEST treatment “per CTTA guidance”.7 Locks and containers are covered in Safes, vaults and GSA containers and What a lock rating promises.

Chapter 2.A.2.b allows AO-approved mitigations for most standards. It adds that some standards “are based upon tested and verified equipment (e.g., a combination lock meeting Federal Specification FF-L 2740) chosen because of special attributes and could not be mitigated with non-tested equipment.”7

Chapter 8 says personal recognition at the entrance is “the ideal access control”. Where continuous visual observation is not possible, an automated system uses two of badge, PIN (“four or more random digits”) and biometric. Its false-acceptance probability must be no more than one in ten thousand and its false-rejection probability no more than one in one thousand, as certified by the manufacturer. Access control systems “shall not be used to secure an unoccupied SCIF”.7

Windows, vents and ducts

Chapter 3.F asks that windows be minimised and requires that they be non-opening and “provide visual and acoustic protection”. Windows “within 18 feet of the ground or an accessible platform” are alarmed. Windows less than 18 feet above the ground or nearest accessible platform are protected against forced entry to the perimeter standard. Windows get RF treatment “when recommended by the CTTA”.7

Chapter 3.G.7 covers vents and ducts, which must meet the SCIF’s acoustic requirements. Vent or duct openings through perimeter walls that “exceed 96 square inches shall be protected with permanently affixed bars or grills”. Protection is not required when one dimension is under six inches or permanent metal baffles are no more than six inches apart. Where protection is used, an access port allows inspection. Utilities serving other areas “shall not transit the SCIF unless mitigated with AO approval”.7

Sound

Chapter 9 protects conversations “from being inadvertently overheard” and “is not intended to protect against deliberate technical interception of audio emanations”.7 Sound Group 3 is “STC 45 or better”: “Loud speech from within the SCIF can be faintly heard but not understood outside of the SCIF.” Sound Group 4 is “STC 50 or better”, for “Very loud sounds ... such as loud singing, brass music, or a radio at full volume” (Chapter 9.B). Where discussion is authorised, the perimeter meets Group 3 and amplified areas such as conference and video teleconference rooms meet Group 4 (Chapter 9.D). Closed storage without discussion has no acoustic requirement (Chapter 3.C.1.c).7 Instrumented tests place the speaker “six feet from the test wall and 4 feet off the floor”. Instrumented testing to NIC 40 or NIC 45 is an alternative, and non-instrumental tests need AO approval (Chapter 9.C).7 Sound masking generators must be permanently installed, contain no AM/FM receiver and have recording capability disabled, and are subject to TSCM inspection (Chapter 9.E).7

Emanations: TEMPEST and RF

NSA’s declassified history “TEMPEST: A Signal Problem” recounts that during the Second World War a Bell Telephone researcher found that a 131-B2 cipher mixer produced spikes on a distant oscilloscope, and “he could read the plain text of the message being enciphered by the machine!”18 In NSA’s account, Bell engineers later recorded a cryptocentre from about 80 feet away and “produced about 75 % of the plain text”, and Bell Labs proposed “Shielding”, “Filtering” and “Masking”.18 The history adds that a later AFSA letter to SIGINT activities gave three options: control a 200-foot zone, operate at least ten teletypes simultaneously as masking, or obtain a waiver. It calls the 200-foot figure “quite arbitrary”.18

The SCIF TEMPEST checklist asks about surroundings. Outside controlled areas it asks for distances “from the SCIF perimeter to the closest limit of SCIF’s inspectable space boundary”. It asks about “any areas within 100 meters of the SCIF which are occupied by Foreign Nationals or controlled by Foreign Entitles/Companies that are not readily accessible by SCIF personnel”. In multi-story buildings not entirely controlled by the U.S. government, it asks who occupies the floors above and below. It also asks for signal lines to be identified “as BLACK or RED”.15 The 2023 UFC defined RED as systems processing national security information, and BLACK as those processing encrypted national security information or non-NSI. It said BLACK lines leaving the inspectable space “are potential carriers of Compromising Emanations (CE)”.16 The 2026 change summary says these definitions moved to commentary.13

TEMPEST countermeasures are a project determination. The CTTA determines “if TEMPEST countermeasures are required”.5 RF protection for walls “shall be installed at the direction of the CTTA when a SCIF utilizes electronic processing and does not provide adequate RF attenuation at the inspectable space boundary”, and is “recommended for all applications where RF interference from the outside of the SCIF is a concern inside the SCIF” (Chapter 3.C.4). Metallic penetrations “may require TEMPEST countermeasures ... when recommended by the CTTA” (Chapter 3.G).7 RF transmitters may not enter a SCIF “unless evaluated and mitigated to be a low risk ... by a competent authority (e.g., CTTA) and approved by the AO”.5 Precision Security Consulting lists CNSSAM TEMPEST/1-13 among restricted documents it names by title only.19 On cost, ICS 705-1 says RF shielding, when required by CTTA evaluation, “should be planned for installation during initial construction as costs are significantly higher to retrofit after construction is complete.”5

Telephones and portable devices

Chapter 11 requires on-hook and off-hook audio protection for unclassified telephones. The protection comes from equipment listed under TSG-6/CNSSI 5006, or from a computerised telephone switch installed under TSG-2/CNSSI 5002. The switch option has conditions. Its protected space must match the SCIF’s security and access control, the AO accepts that on-hook audio may be present on wiring up to the switch, and CNSSI 5006 instruments are required unless the switch’s administration terminals are in a controlled area and safeguarded against unauthorised manipulation. Telephones that are not type-accepted are presumed to carry on-hook audio until a technical investigation shows otherwise. Speakerphones are not used on unclassified systems unless the AO approves an exception. Where requirements cannot be met, unclassified telephones go in non-discussion areas only.7

Chapter 10 classifies portable devices by function, mitigation and residual risk. Low-risk devices, with no recording or transmission capability, may be admitted without mitigation. Medium-risk devices have recording or transmitting features that “can be physically disabled”, including “Devices that have microphones or recording capabilities”. High-risk devices need more extensive mitigation or cannot be mitigated. They include RF-transmitting devices, “Photographic, video, and audio recording devices” and “Multi-function cellular telephones”. For these the AO may approve “government- and contractor-owned” devices “for official business provided mitigation measures are in place that reduces the risk to low”. Personally owned devices are prohibited in SCIFs outside the United States. IC element heads that allow medium- or high-risk devices run a mitigation programme whose user agreement lets the government seize a device “for physical and forensic examination”. Device decisions “are not reciprocal”.7

Alarms and response time

Alarm details are in Detect, assess, respond. ICS 705-1 §G.2.c requires IDS installation, components and monitoring stations to “comply with Underwriters Laboratories (UL) 2050 Extent 3 standards”. Systems developed and used exclusively by the U.S. government are exempt from UL certification and still must meet the UL 2050 Extent 3 installation standard, and “Contractor SCIFs shall maintain a current UL certificate of installation and service”.5 For contractor systems under the NISPOM rule, the Cognizant Security Agency approves an IDS before installation. It bases approval on ICD 705 and any applicable IC standard and UL 2050, “or the CSA may base approval on written CSA-specific standards”.20

For SCIFs in the United States, Chapter 3.H sets response times: closed storage, 15 minutes; open storage, 15 minutes with security-in-depth “or a five minute alarm response time if it is not”. SWAs have 15 minutes (Chapter 3.I). Overseas times are in Chapters 4 and 5.7

Security-in-depth is “the factors that enhance the probability of detection before actual penetration to the SCIF occurs”. The AO “may” accept such layers, and “with AO approval” they may “alter construction requirements and extend security alarm response time to the maximum of 15 minutes” (Chapter 2.B.1). Chapter 2.B.3 lists qualifying layers, such as installations or compounds “with a dedicated response force of U.S. persons”, controlled buildings, alarmed surrounding office areas and fenced compounds with controlled gates.7 Overseas, Chapter 4 pairs Wall B or C, described as giving “five minutes of forced-entry protection”, with five-minute response for some open storage.7 Read together, the provisions match barrier delay to response time. That is an interpretation, and the spec states no such rule. Choosing protection from a design-basis threat is covered in How a facility’s security is decided.

Construction security and personnel

ICS 705-1 §F.5 says construction and design “shall be performed by U.S. companies using U.S. persons”, with AO-documented mitigations for non-U.S. citizens.5 Tech Spec Chapter 3.B.5 says work “should be performed by U.S. companies using U.S. citizens to reduce risk, but may be performed by U.S. companies using U.S. persons”, with mitigations in the CSP. Domestic controls are the CSP, site access control, barriers during renovations and SSM inspections.7

Overseas SCIFs not under Chief of Mission authority have site-specific rules in Chapter 4.C and 4.D.7 Workers from countries at the “critical technical threat level” are prohibited. Finish work is done by SECRET-cleared U.S. personnel in Category III and TOP SECRET-cleared U.S. personnel in Categories I and II. Uncleared workers provide biographical data and fingerprints as local law allows. “Maximum demolition” applies when expanding into space not controlled at SECRET, and guards are required. ICS 705-1 §G.4 adds procedures in the CSP for procuring, shipping, storing and inspecting material.5 Chapter 5 covers Chief of Mission facilities.7

In operation, Chapter 12.J requires visitor logs “retained for two years after the date of the last entry”. Clearances are verified through Scattered Castles “to the greatest extent possible”. Uncleared personnel are escorted, with escort ratios set case by case by the SO. Emergency personnel are “escorted to the degree practical”.7 TSCM in SCIFs “will only be conducted by USG TSCM teams established or sponsored by a USG element”, which may include trained U.S. government contractors (Chapter 12.G.8).7

Inside and outside the United States

Security-in-depth “is mandatory for SCIFs located outside the United States due to increased threat”.5 Chief of Mission facilities follow the ICD 705 series and the Overseas Security Policy Board standards in 12 FAH-6, with the more restrictive applying. OSPB waivers go to the State Department’s Bureau of Diplomatic Security before construction, renovation or operations.457 For other overseas SCIFs, the State Department’s threat list sets a construction category.

Category (Tech Spec 1.5.1, Chapter 4.B)DefinitionExamples of what changes
I“Critical or High Technical Threat, High Vulnerability Buildings”Open storage “to be avoided”, with mission-essential need certified and open storage approved case by case by the element head. SCI must be “contained within approved vaults or Class M or greater modular vaults”; SWAs and TSWAs “not authorized”
II“High Technical Threat, Low Vulnerability Buildings”Open storage to be avoided and approved case by case by the element head; TOP SECRET-cleared finish trades
III“Low and Medium Technical Threat”Open storage “should only be allowed” when the host facility has 24-hour cleared U.S. staffing or the SCIF itself is continuously occupied by “U.S. SCI-indoctrinated personnel”; SECRET-cleared finish trades

Security-in-depth “may allow AOs to deviate from this guidance at Category II and III facilities” (Chapter 4.A.2).7 In the United States, whether a leased suite in a multi-tenant building qualifies for security-in-depth depends on Chapter 2.B and the AO’s acceptance. The answer affects the wall, the response time and the TEMPEST checklist’s questions about neighbours.715

Operating the facility

Chapter 12 sets the routine.7 The SO writes an AO-approved operating procedure and reviews it at least annually, runs annual self-inspections, and controls keys. Emergency drills are held “as circumstances warrant, but at least annually”. Chapters 4 and 5 require semi-annual emergency-plan testing for specified overseas facilities. Combinations “should be changed” when a lock is first used, when compromise is suspected, and when a person who knows the combination no longer requires access “unless other sufficient controls exist to prevent access to the lock”. A lock taken out of service is reset to 50-25-50. Alarm annunciation records are kept two years, and the SCIF repository is updated within 30 days of a change.

Three kinds of review apply. The AO or a designee inspects before accreditation (Chapter 12.G.1). The AO or designee also inspects periodically, based on threat and other factors, “or at least every five years” (Chapter 12.G.3). Under ICS 705-02, the CSA ensures re-evaluations at least every five years and reports re-accreditation results to NCSC within 30 days.73 If an AO finds conditions unsatisfactory, accreditation “may be suspended or revoked”. Authorities and occupants are “immediately notified and the SCIF closed until deficient conditions are corrected”, and “All SCI material shall be relocated to another SCIF” (Chapter 12.E).7 Under ICD 705 a SCIF must be accredited before SCI use, so a revoked facility needs accreditation again.1

De-accreditation (Chapter 12.I) means inspecting for and removing material, resetting containers to 50-25-50 with written certification, and handling equipment and media “in accordance with AO guidance” or “as approved by the AO”. The closeout procedures call for requesting revocation of the system and SCIF accreditations. Alarm service is transferred when the facility is reused for another mission or project that requires it, and discontinued when there is no such reuse and the classified, sensitive or proprietary information has been removed.7 Re-accreditation under a previous standard is narrow. ICS 705-1 §C.2.c allows SCIFs “de-accredited for less than one year but continuously controlled at least at the Secret level” to be re-accredited “one time”. ICS 705-02 adds “with the AO’s approval”.53

Sharing a SCIF: reciprocity, co-use and joint use

ICD 705 says SCIFs “accredited without a waiver of the uniform security requirements shall be available for reciprocal use”.4 ICS 705-1 says “A waiver for standards that cannot be met removes a SCIF from mandatory reciprocal use.”5

ICS 705-02 §E separates reciprocal acceptance from shared use.3 A SCIF accredited without waivers is “reciprocally accepted for use as accredited by all IC elements”. Use by an organisation sponsored by another IC element normally needs a co-use agreement, which is called joint use if the tenant uses the host’s information system. The agreement is signed by the tenant’s and host’s AOs or designees and routed through co-use coordinators. The exceptions are:

  • components under the same IC element need no agreement;
  • SCI may be stored temporarily for others “for up to seven calendar days”;
  • the special security officer may lend conference rooms for occasional SCI discussions.

In an accredited contractor SCIF, “a co-use agreement is required for each contracting effort (e.g., contracts, proposals)”. A contractor proposing to an agency other than the host CSA “must obtain an appropriate government sponsor”, and both CSAs must approve the co-use request (§E.3.g). The tenant accepts the host’s accreditation. Modifications for a different type or use are paid by the tenant “unless an alternate agreement is reached”. The host CSA keeps security cognizance unless both CSAs approve a transfer.3

SAPFs and the SCIF specification

Volume 3 of DoDM 5205.07 (2015, Change 3 of 2020), Enclosure 3, paragraph 1.b(2), said the Tech Spec and ICD 705 “are the physical standards for protection of SAP information”. It said SAP facilities “will conform to the equivalent” SCIF types “unless variations are specifically noted in this volume”.21 The 17 January 2025 manual cancelled Volume 3.2 Its §15.3.b says SAP areas “will conform to the equivalent facilities as defined in the NCSC SCIF Specifications in effect at the time the SAP area is initially accredited, unless variations are specifically noted in this issuance”. Under §15.3.d, the CA SAPCO approves “waivers for imposing safeguards that exceed standards outlined in ICD 705 series policy, even when the additional safeguards are based on risk”. Under §15.8.i, space used for both SCI and SAP “must be accredited as a SAPF ... and as a SCIF in accordance with ICD 705”, with a co-use agreement.2

Section 15.2 is narrower. A CA SAPCO may accept existing accreditations of DoD-accredited SCIFs, temporary SCIFs and SCI working areas, and of “Permanent SCIFs accredited, operated, and occupied by a non-DoD IC element”. The SAPCO may then authorise SAP discussion in private offices and conference rooms there. That use is at the SCIF special security officer’s discretion. Everyone present must hold the relevant SAP access, and non-briefed people must not be able to overhear. Standalone SAP IT needs prior approval from the SSO and the programme security manager or officer. Processing in the designated offices or conference rooms needs prior approval from the CA SAPCO or designee. SAP materials “may not be printed or stored in a SCIF” without meeting §15.1.c.2 On the SCIF side, a SAPF co-utilised as a SCIF takes “the highest requirement of the two” (Tech Spec 1.B).7

What changed in 2025 and 2026: published and reported

A search on 27 November 2026 covered ODNI’s archived NCSC policy page, the Wayback Machine’s captures of dni.gov and archive.dni.gov files, and the Federal Register. It found no public text of a 2025 or 2026 SCIF memo and no specification newer than 1.5.1. The ODNI page states that it is archived and no longer updated.11 This is the result of one dated search, not proof that the memos do not exist.

DateClaimSource and typeConfidence
20 Feb 2024Technical amendment to ICD 705 reflecting NCSCPublished directive4Published
17 Jan 2025DoDM 5205.07 reissued; SAP physical volume cancelledPublished manual2Published
15 Jan 2025ODNI memo: “Rescinds authorization for reaccreditation under previous standards”; “Review of all SCIFs and identification of upgrades required NLT 31 DEC 2025”; “Upgrades required to be complete NLT 31 DEC 2028”AECOM conference slide, 5 March 202622Reported; no memo text
Feb 2025Memo includes a risk table and a POA&M template that owners “may” use, aimed at “grandfathered DCID 6/9 and even DCID 1/21 SCIFs/SAPFs”SPG consultancy23Reported; does not show the scope of any mandatory POA&M
Apr 2025Inventories, risk assessments and POA&Ms by 2025, with budget planning through 2028. CenCore quotes the memo as saying “there is very little published guidance on TEMPEST”CenCore, a modular-SCIF vendor24Reported in marketing; the quotation is CenCore’s
Oct and Dec 2025ODNI “updated” ICD 705 in 2025 with RF shielding and TEMPEST changes; “many (if not most) existing SCIFs will require a complete rebuild”Holland & Knight;25 JLL26Characterisation; no published revision found. Holland & Knight also dates ICD 705 to 2008, but it was signed in 2010
4 May 2026NCSC memo rescinded the POA&M requirement; “ICD 705 version 1.5.1 remains the governing baseline”; a revised version is “forthcoming”Cushman & Wakefield27Reported; its compliance outlook is labelled “In our opinion”
Oct 2026“industry sources report” the 4 May memo; it “hasn’t been publicly released”; “no new standard has been published”Precision Security Consulting19Second-hand report
Jul 2026A January 2025 memorandum required SCIFs and SAPFs in the United States to meet ICD 705 by the end of 2028; the article does not discuss any May 2026 memoIsaac Fisher, guest author for SIA28Repeats the January report; does not show a deadline survived

The accounts disagree in kind, not only in detail. AECOM, SPG, CenCore and Fisher describe a compliance process for existing and legacy facilities. Holland & Knight and JLL describe new binding design requirements, which no document published as of 27 November 2026 contains. The rescission is reported by one real-estate firm and, at second hand, one consultancy. Whether grandfathering has ended, whether any 2028 date applies to a given facility, and what the POA&M rescission covered are all unverified.

The RF question

The detailed history of RF practice comes from one consultancy, Precision Security Consulting. It says that around 2018 and 2019 “some CSAs would ask for real shielding performance, with numbers in the 60 to 80 dB range coming up in conversation. Nothing was published”. It says that around 2020 “one large DoD CSA directed that its spaces be treated on all six sides, and walked it back almost as quickly”.29 These are unverified accounts of unpublished practice. Under the public documents, exceeding a standard “even when based upon risk, requires that a waiver be processed and approved in accordance with ICD 705” (Chapter 2.A.2.c). DoD calls this a “waiver up”.78 For a particular room, RF treatment is set by the CTTA’s recommendation and the AO’s approval.

Baseline and project decisions

Public documentsDecided for the project, and by whom
Accreditation by a named AO; waivers by a different official; mandatory reciprocity lost with a waiver for standards that cannot be met (ICD 705; ICS 705-1 §H)45Whether TEMPEST countermeasures are needed: CTTA recommends, AO approves (ICS 705-1; Tech Spec 3.C.4)57
Perimeter includes floor and ceiling, with visual evidence of penetration (ICS 705-1 §G.1)5Acceptance of security-in-depth: AO (Tech Spec 2.B)7
Where discussion is authorised, Sound Group 3 perimeter and Group 4 for amplified areas (Tech Spec 9.D)7Alternative construction and mitigations: AO, recorded in the FFC (Tech Spec 2.A; DoDM 5105.21 V2)78
One primary door; FF-L-2740 lock; FF-L-2890 hardware (Tech Spec 3.E)7Devices allowed inside: AO, with CTTA for transmitters (Tech Spec 10)7
Vent and duct openings through perimeter walls over 96 square inches protected, with exceptions (3.G.7.c); windows non-opening with visual and acoustic protection, alarmed within 18 feet of the ground or an accessible platform, and protected against forced entry at less than 18 feet (3.F)7Acoustic test method: non-instrumental tests need AO approval (Tech Spec 9.C)7
UL 2050 Extent 3; current UL certificate for contractor SCIFs; domestic response times (ICS 705-1 §G.2.c; Tech Spec 3.H)57Alarm for a TSWA; TSCM for a new or renovated SCIF: AO (Tech Spec 3.J; ICS 705-02)73
CSP approved before contract award; FFC, SOP, emergency plan; re-evaluation at least every five years (Tech Spec 3.B; ICS 705-02)73Escort ratios: SO (Tech Spec 12.J). CST use and material controls: set in the CSP (Tech Spec 4)7
SAP areas follow the specification in effect at initial accreditation, with stated variations (DoDM 5205.07 §15.3.b)2Co-use terms, including who pays for modifications (ICS 705-02 §E)3

Several decisions depend on sponsor confirmation before design starts: which specification edition and DoD criteria edition govern; whether the January 2025 and May 2026 memos apply to the facility and what they require; whether a legacy room can keep its earlier accreditation basis; and what RF treatment the CTTA requires.

Cost, time and the market

The published figures come from firms that sell SCIF services or advice. None of the cited pages gives underlying data.

  • Construction only. Precision Security Consulting: a typical SCIF or SAPF construction contract runs “six months to a year depending on size”, after design and before accreditation.29
  • Accreditation only. Holland & Knight: “accreditation itself typically takes 12 to 18 months and possibly longer given the expected increase in demand for the new standard”.25 JLL: accreditation “can stretch up to 36 months under the new standards”.26
  • Whole project. Cushman & Wakefield: “planning, construction, and accreditation require 12 to 24 months or longer”.27
  • Cost. JLL: “Costs range from $350–$1,000 per square foot”.26 SPG, of large organisations upgrading to a timetable: “These costs can be in the tens of millions of dollars”.23 Fisher, as a guest author for SIA, puts an ICD 705-compliant area at “several times” the cost of a traditional office, without giving a basis.28

The Holland & Knight and JLL figures are tied to their description of a 2025 technical revision that no public document contains as of 27 November 2026. They cannot price a current compliance obligation. The documents show where requirements add work. RF shielding, where the CTTA requires it, is cheaper to build in than to retrofit.5 Open storage without security-in-depth adds forced-entry construction, amplified discussion adds Sound Group 4, and overseas construction security adds cleared trades and surveillance.7

Leasing

A contractor’s commercial lease and a government lease create different obligations. Holland & Knight advises contractor tenants to review alterations clauses and to negotiate SCIF maintenance, landlord pre-approval of government-required upgrades, and “termination options if required building upgrades are unable to be completed”.25 GSA’s model Global Lease L100 (May 2026) has a clause, §2.03, that is operative only where it is incorporated in an executed government lease. Under it, the lessor “must have no right to require the Government to restore the Premises upon expiration or earlier termination (full or partial) of the Lease”. The lessor also waives claims arising from “The Government’s normal and customary use of the Premises” and from “Any initial or subsequent alteration to the Premises”.30 A contractor’s commercial lease contains such terms only if the parties negotiate them. Within a SCIF, ICS 705-02 makes a co-use tenant pay for modifications it needs “unless an alternate agreement is reached”.3

Shared SCIFs, SCIF-as-a-service and modular units

Leasing space in a building does not convey SCIF authorisation. In a shared or commercially operated SCIF, cross-organisation use normally rests on a co-use agreement approved by both AOs or designees, subject to the exceptions in ICS 705-02 §E (same-element components, seven-day temporary storage, occasional conference-room discussions). A contractor SCIF needs an agreement for each contracting effort, and proposals to a non-host agency need a sponsor and both CSAs’ approval. The host CSA keeps cognizance unless a transfer is approved.3 The tenant accepts the host’s accreditation. Mandatory reciprocity depends on whether the host holds waivers for standards that cannot be met.53 JLL markets “SCIF-as-a-Service options”.26 One modular vendor says its units “meet or exceed all ICD705 and TEMPEST security requirements”.24 The Tech Spec’s warning about such claims applies, and each unit is accredited by an AO.7

What to do now

  1. Confirm the governing documents with the sponsor, then record them. Ask which editions govern: ICD 705 as amended in 2024, Tech Spec 1.5.1 or any newer direction, and for DoD the applicable UFC edition. Record the confirmed basis in the CSP and FFC. The SAP manual ties SAP areas to the specification “in effect at the time the SAP area is initially accredited”.47102
  2. Bring in the AO and CTTA before design is fixed. Submit the Pre-Construction and TEMPEST checklists early, since RF shielding, where required, costs more to retrofit.14155
  3. Treat future RF provisions as an option to evaluate. Ask the AO and CTTA whether to leave room for later RF treatment at this site. Industry forecasts are unverified.729
  4. Get the memos through the sponsor. Ask the government sponsor’s security office or AO for the January 2025 and May 2026 memos and their effect on the facility.222719
  5. Match the accreditation type to the contracts. A room accredited for less is not reciprocal for more, and each added capability brings requirements.5
  6. Record each legacy room’s accreditation basis, its waivers and its actual RF treatment.423
  7. Settle who pays in each agreement. Cover alterations, government-required upgrades, termination and restoration in the lease. In each co-use agreement, record whether the tenant pays for modifications or an alternate agreement applies.25303
  8. Audit to the public documents. Check that the accreditation letter shows storage type, acoustic status and waivers. Check that the FFC, CSP, SOP and emergency plan are current, that a contractor SCIF holds a current UL certificate of installation and service, that self-inspections are annual and AO inspections within five years, and that repository updates are made within 30 days.375

Conclusion

A SCIF is an accredited area, room, group of rooms, building or installation. The public documents behind it are ICD 705 as amended in 2024, ICS 705-1, ICS 705-02 and Tech Spec 1.5.1. They are specific about perimeter, sound, doors, penetrations, alarms, construction security and records, and allow AO-approved alternatives. TEMPEST countermeasures, security-in-depth, device policy and many mitigations are decided for each project: the CTTA recommends, the AO approves, and a separate official decides waivers. How these decisions affect a particular project’s cost is not set by the documents alone. Industry accounts of the reported 2025 and 2026 policy changes differ on whether they concern compliance for existing facilities or new design requirements. A dated public search found neither memo and no newer specification. Someone planning, leasing, building or auditing a SCIF should confirm the governing documents and directions with the sponsor, get the AO’s and CTTA’s decisions in writing, and obtain the memos through the sponsor, not from commercial summaries.

Footnotes

  1. Intelligence Community Directive 705, “Sensitive Compartmented Information Facilities”, Office of the Director of National Intelligence, signed 26 May 2010, sections B and D (original 2010 text, copy on intelligence.gov). https://www.intelligence.gov/assets/documents/intelligence-community-directives/ICD_705.pdf (opens in a new tab) ↩1 ↩2 ↩3 ↩4 ↩5 ↩6 ↩7
  2. DoD Manual 5205.07, “Special Access Program Security Manual”, Office of the Under Secretary of Defense for Intelligence and Security, effective 17 January 2025, paragraph 1.2, Section 15 (paragraphs 15.2, 15.3.b, 15.3.d, 15.8.i) and Glossary G.2 (“SCIF”) (archived copy, 1 February 2026). https://web.archive.org/web/20260201215016/https://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodm/520507m1.PDF?ver=o_3_m4lDAtLKPOLQHatcYA%3D%3D (opens in a new tab) ↩1 ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8
  3. Intelligence Community Standard 705-02, “Standards for the Accreditation and Reciprocal Use of Sensitive Compartmented Information Facilities”, National Counterintelligence and Security Center, 22 December 2016, sections D and E (archived copy, 18 October 2017). https://web.archive.org/web/20171018165045/https://www.dni.gov/files/NCSC/documents/Regulations/ICS_705-2_Standards_for_Accreditation_Reciprocal_Use_of_SCIFs.pdf (opens in a new tab) ↩1 ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8 ↩9 ↩10 ↩11 ↩12 ↩13 ↩14 ↩15
  4. “Intelligence Community Directive 705 Technical Amendment”, ODNI, signed 20 February 2024 by the Assistant Director for Policy & Strategy, sections A and B, followed by the amended text of ICD 705, sections D.2 to D.9 (archive.dni.gov copy). https://archive.dni.gov/files/documents/ICD/ICD-705-SCIFs.pdf (opens in a new tab) ↩1 ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8 ↩9 ↩10 ↩11
  5. Intelligence Community Standard 705-1, “Physical and Technical Security Standards for Sensitive Compartmented Information Facilities”, ODNI, effective 17 September 2010, sections B to J (scanned document; archived copy of the archive.dni.gov file, 4 September 2026). https://web.archive.org/web/20260904051825/https://archive.dni.gov/files/NCSC/documents/Regulations/ICS-705-1.pdf (opens in a new tab) ↩1 ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8 ↩9 ↩10 ↩11 ↩12 ↩13 ↩14 ↩15 ↩16 ↩17 ↩18 ↩19 ↩20 ↩21 ↩22 ↩23 ↩24 ↩25 ↩26 ↩27 ↩28 ↩29 ↩30 ↩31 ↩32 ↩33 ↩34 ↩35 ↩36 ↩37
  6. “Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities, Version 1.5”, National Counterintelligence and Security Center, 13 March 2020 (memorandum NCSC 19-686 and Chapter 2.C.2.c) (archived copy, 31 December 2025). https://web.archive.org/web/20251231021052/https://www.dni.gov/files/Governance/IC-Tech-Specs-for-Const-and-Mgmt-of-SCIFs-v15.pdf (opens in a new tab) ↩1 ↩2 ↩3
  7. “Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities, Version 1.5.1”, National Counterintelligence and Security Center, 26 July 2021 (memorandum NCSC-2021-00068, change history, table of contents and Chapters 1 to 13) (archived copy of the archive.dni.gov file, 3 September 2026). https://web.archive.org/web/20260903204125/https://archive.dni.gov/files/NCSC/documents/Regulations/IC_Technical_Specifications_for_Construction_and_Management_of_Sensitive_Compartmented_Information_Facilities_v151_PDF.pdf (opens in a new tab) ↩1 ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8 ↩9 ↩10 ↩11 ↩12 ↩13 ↩14 ↩15 ↩16 ↩17 ↩18 ↩19 ↩20 ↩21 ↩22 ↩23 ↩24 ↩25 ↩26 ↩27 ↩28 ↩29 ↩30 ↩31 ↩32 ↩33 ↩34 ↩35 ↩36 ↩37 ↩38 ↩39 ↩40 ↩41 ↩42 ↩43 ↩44 ↩45 ↩46 ↩47 ↩48 ↩49 ↩50 ↩51 ↩52 ↩53 ↩54 ↩55 ↩56 ↩57 ↩58 ↩59 ↩60 ↩61 ↩62 ↩63
  8. DoD Manual 5105.21, Volume 2, “Sensitive Compartmented Information (SCI) Administrative Security Manual: Administration of Physical Security, Visitor Control, and Technical Security”, 19 October 2012, incorporating Change 2 effective 2 November 2020, Enclosure 2, paragraphs 1.a to 1.f (archived copy, 8 December 2021). https://web.archive.org/web/20211208042549/https://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodm/510521m_vol2.pdf (opens in a new tab) ↩1 ↩2 ↩3 ↩4 ↩5 ↩6 ↩7
  9. 32 CFR Part 117, “National Industrial Security Program Operating Manual (NISPOM)”, sections 117.3 (Cognizant Security Agency) and 117.23(a)(1) and (b), eCFR, text current to 24 November 2026; the cited provisions also appear in the 2025 annual CFR edition on GovInfo (opens in a new tab). https://www.ecfr.gov/current/title-32/subtitle-A/chapter-I/subchapter-D/part-117 (opens in a new tab) ↩1 ↩2 ↩3
  10. WBDG document catalogue entries “UFC 4-010-05 SCIF/SAPF Planning, Design, and Construction” (status ACTIVE, publish date 30 September 2026, “Digital UFC Content is active for project delivery teams”) and “UFS 4-010-05 SCIF/SAPF Planning, Design, and Construction” (status ACTIVE, publish date 30 September 2026), retrieved from the WBDG catalogue data service, 27 November 2026. https://www.wbdg.org/api/documents?search=4-010-05 (opens in a new tab) ↩1 ↩2 ↩3
  11. “NCSC CI and Security Governance Regulations” (archived NCSC policy page listing ICS 705-01, ICS 705-02, Tech Spec 1.5.1 and version 1.5 checklists and forms; states it is archived and no longer updated), ODNI, accessed 27 November 2026. https://archive.dni.gov/index.php/ncsc-how-we-work/ncsc-ci-security-governance-regulations (opens in a new tab) ↩1 ↩2 ↩3
  12. “UFC 4-010-05 SCIF/SAPF Planning, Design, and Construction” (catalogue entry: status Active, publish date 05/26/2023), WBDG legacy site, accessed 27 November 2026. https://legacy.wbdg.org/dod/ufc/ufc-4-010-05 (opens in a new tab) ↩
  13. “Change Summary for UFC 4-010-05 SCIF/SAPF Planning, Design, and Construction”, 1 September 2026 (provided for information only; entries for 3-4, 3-4.21.3 and 3-4.22.8), WBDG related material. https://nibs-s3-wbdg3-production.s3.us-east-1.amazonaws.com/media/2026-11/UFC_4-010-05_Change_Summary_1793982636403_jglsluei4aq.pdf (opens in a new tab) ↩1 ↩2
  14. “SCIF Pre-Construction Checklist” (Tech Spec version 1.5 form), ODNI, introduction (archived copy of the archive.dni.gov file, 11 August 2026). https://web.archive.org/web/20260811151646/https://archive.dni.gov/files/Governance/SCIF-Pre-Construction-Checklist-V15.pdf (opens in a new tab) ↩1 ↩2
  15. “SCIF TEMPEST Checklist” (Tech Spec version 1.5 form), ODNI, attachments (external and internal maps) and Section B (archived copy of the archive.dni.gov file, 11 August 2026). https://web.archive.org/web/20260811143548/https://archive.dni.gov/files/Governance/SCIF-TEMPEST-Checklist-V15.pdf (opens in a new tab) ↩1 ↩2 ↩3 ↩4
  16. UFC 4-010-05, “SCIF/SAPF Planning, Design, and Construction”, Unified Facilities Criteria (NAVFAC preparing activity), 26 May 2023 edition, paragraphs 1-19.3 and 3-4.22.3 (historical edition). https://www.wbdg.org/FFC/DOD/UFC/ufc_4_010_05_2023.pdf (opens in a new tab) ↩1 ↩2
  17. DoD Instruction 5200.48, “Controlled Unclassified Information (CUI)”, effective 6 March 2020, paragraph 3.2 (legacy information) and marking requirements (archived copy, 31 May 2026). https://web.archive.org/web/20260531063810/https://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodi/520048p.pdf (opens in a new tab) ↩
  18. “TEMPEST: A Signal Problem”, Cryptologic Spectrum, National Security Agency (declassified article; no issue date on the released copy) (archived copy, 31 October 2026). https://web.archive.org/web/20261031065843/https://www.nsa.gov/portals/75/documents/news-features/declassified-documents/cryptologic-spectrum/tempest.pdf (opens in a new tab) ↩1 ↩2 ↩3
  19. Phillip Chance, “Heard There’s a New SCIF Policy? Check the ICD 705 Policy Library First”, Precision Security Consulting, 27 October 2026. https://www.psc-consultant.com/post/heard-there-s-a-new-scif-policy-check-the-icd-705-policy-library-first (opens in a new tab) ↩1 ↩2 ↩3
  20. 32 CFR 117.15, “Safeguarding classified information”, paragraph (d)(1)(i), eCFR, text current to 24 November 2026; the cited provision also appears in the 2025 annual CFR edition on GovInfo (opens in a new tab). https://www.ecfr.gov/current/title-32/subtitle-A/chapter-I/subchapter-D/part-117/section-117.15 (opens in a new tab) ↩
  21. DoD Manual 5205.07, Volume 3, “DoD Special Access Program (SAP) Security Manual: Physical Security”, 23 April 2015, incorporating Change 3 effective 8 December 2020, Enclosure 3, paragraph 1.b(2) (archived copy, 18 March 2021). https://web.archive.org/web/20210318062315/https://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodm/520507_vol03.PDF?ver=iJ-eGWUCqX4IeO_5QOkZ5g%3d%3d (opens in a new tab) ↩
  22. Timothy M. Conley, Peter Brown, Jennifer Ramirez and Cory Bonham (AECOM), “Concept to Clearance: Navigating ICD 705 from Planning to Accreditation”, Society of American Military Engineers conference session, 5 March 2026, slide “ODNI Memo – 15 JAN 2025”. https://www.same.org/wp-content/uploads/2026/03/42_1400-1500_thu_gold_concept_to_clearance.pdf (opens in a new tab) ↩1 ↩2
  23. Jason Phillippe, “POAMs: Intelligence Community Directive 705, Compliance Requirements and Plans of Action”, SPG, 7 February 2025, updated 12 March 2025. https://www.spgsecure.com/post/poams-intelligence-community-directive-705-compliance-requirements-and-plans-of-action (opens in a new tab) ↩1 ↩2 ↩3
  24. “ICD 705 SCIF Compliance Challenges: How the ODNI Memo Sparked the SCIF-Pocalypse”, CenCore Group (modular SCIF vendor), 4 April 2025. https://cencoregroup.com/icd-705-scif-odni-memo-tempest-impact/ (opens in a new tab) ↩1 ↩2
  25. Briana Becker, Gordon Griffin and Susannah L. Gilmore, “Leasing SCIF Space: How the New ICD-705 Affects Leases”, Holland & Knight Alert, 30 October 2025. https://www.hklaw.com/en/insights/publications/2025/10/leasing-scif-space-how-the-new-icd-705-affects-leases (opens in a new tab) ↩1 ↩2 ↩3 ↩4
  26. “Navigating the New Era of SCIF Construction: Compliance, Security & Strategy”, JLL, 17 December 2025. https://www.jll.com/en-us/insights/navigating-the-new-era-of-scif-construction-compliance-security-and-strategy (opens in a new tab) ↩1 ↩2 ↩3 ↩4
  27. Amjad Jariri and Angela Poliskey, “ICD 705 POA&M Rescission: Less Certainty, Not Less Compliance”, Cushman & Wakefield, 2026 (no date shown on the page; refers to the memo of 4 May 2026), accessed 27 November 2026. https://www.cushmanwakefield.com/en/united-states/insights/icd-705-poam-rescission (opens in a new tab) ↩1 ↩2 ↩3
  28. Isaac Fisher (Honeywell Aerospace), “Modernizing the Secure Area”, SIA RISE Resource, Security Industry Association, July 2026, section “ICD 705 Modernization”. https://www.securityindustry.org/wp-content/uploads/2026/07/RISE-Resource-30.pdf (opens in a new tab) ↩1 ↩2
  29. Phillip Chance, “You’ve Lived Through Six Years of RF Whiplash. Here’s What You Know Now.” (ICD 705 RF shielding: what changed 2018 to 2026), Precision Security Consulting, 20 October 2026. https://www.psc-consultant.com/post/icd-705-rf-shielding-timeline (opens in a new tab) ↩1 ↩2 ↩3
  30. “Global Lease, GSA Template L100 (5/2026)”, U.S. General Services Administration, May 2026, §2.03 “Waiver of Restoration (FEB 2026)” (model lease template). https://www.gsa.gov/system/files?file=Global+Lease+Template+L100+%28May+2026%29_0.pdf (opens in a new tab) ↩1 ↩2